Ask what the installer needs to see
The next trade may need access to backing, framing or floor layers to assess reconstruction. Ask for a clear description of the required condition. Removing visible tile does not establish that every underlying layer is ready for a new system.
Separate removal from repair
Assign responsibility for substrate repairs, new waterproofing, plumbing and electrical work. If the installer expects further preparation, include it in the overall project plan without silently adding it to demolition.
Define the decision point
Agree who reviews newly exposed conditions and what information they need. A photograph can document what is visible but cannot replace a professional judgement about suitability. If the scope needs to change, record the revised boundary before authorising additional removal.
Keep a short handover record
Record the agreed completed removal, retained items and unresolved questions. Share this with the next trade before they start. Avoid describing the room as ready for installation unless the responsible installer has accepted the condition.
Tile removal is not a waterproofing handover
Ask the installer to distinguish the visible tile, the layer it is fixed to and the waterproofing system. Do they need the backing exposed for review, or a wider removal boundary? Who accepts the transition to a retained shower or floor? Keep those answers in the scope. A photograph of a stripped room cannot establish that a remaining waterproofing layer is suitable for reuse.